Board Meeting PowerPoint Presentation
- Project Removal from Accelerated Repair Program
District | School | Invitation Date |
Hanover | Cedar Elementary School | June 26, 2019 |
- Authorization to Execute Project Funding Agreement - Accelerated Repair Program, Estimated Maximum Total Facilities Grants of $24,359,096
District | School | Scope |
Total Project Budget |
Estimated Maximum Total Facilities Grant |
Agawam |
Agawam Junior High School |
Boiler | $1,205,806 | $617,862 |
Blackstone Valley |
Blackstone Valley Regional Vocational Technical High School |
Partial Roof | $1,486,419 | $751,188 |
Chelmsford | South Row Elementary School |
Partial Roof | $516,646 | $248,997 |
Dracut | Brookside Elementary School |
Roof | $3,536,208 | $1,745,262 |
George H. Englesby Elementary School | Roof | $2,806,808 | $1,446,863 | |
East Bridgewater | Central Elementary School | Partial Roof | $2,222,224 | $1,123,134 |
Fitchburg | South Street Elementary School | Partial Roof; Partial Boiler | $3,105,244 | $2,370,144 |
Hampden-Wilbraham Regional School District | Wilbraham Middle School | Roof | $3,169,773 | $1,575,085 |
Lowell | Frederic T. Greenhalge Elementary School | Boiler | $1,479,485 | $1,035,368 |
James S. Daley Middle School |
Boiler | $1,880,962 | $1,311,532 | |
Rogers Early Learning Center |
Boiler | $2,135,646 | $1,505,076 | |
S. Christa McAuliffe Elementary School | Boiler | $1,498,147 | $1,026,312 | |
Southborough | Mary E. Finn Elementary School | Boiler | $1,155,908 | $365,276 |
Wakefield | Greenwood School | Roof | $1,675,490 | $677,556 |
Wayland | Loker Elementary School | Partial Roof | $$3,798,498 | $1,178,571 |
Worcester | Burncoat Street Preparatory School |
Partial Roof | $1,017,713 | $770,685 |
Lincoln Street School | Boiler | $1,346,274 | $1,017,257 | |
Tatnuck Magnet School | Roof | $2,025,697 | $1,518,616 | |
Vernon Hill School | Roof | $2,504,165 | $1,878,257 | |
Worcester East Middle School |
Roof | $2,968,689 | $2,196,055 | |
Totals | $41,535,802 | $24,359,096 |
District | School |
Norwood | Dr. Philip O. Coakley Middle School |
Tyngsborough | Tyngsborough Middle School |
- Invitation to Project Scope and Budget - Estimated Maximum Total Facilities Grants of $153,946,387
District | School | Scope |
Total Project Budget |
Estimated Maximum Total Facilities Grant |
Nauset Regional School District |
Nauset Regional High School | Add/Reno | $131,825,665 | $35,572,564 |
Waltham | Waltham High School | New | $374,567,387 | $118,373,814 |
Totals | $506,393,052 | $153,946,387 |
AUDIT
- Audit Status Report
- Approval of Final Audits with no appeals, MSBA Capital Pipeline Projects grants of $28,535,797
District | School | Scope | Total Project Budget | Total Facilities Grant |
Carver | Carver Elementary School | New Construction | $48,348,872 | $25,248,602 |
Provincetown | Provincetown High | Repair | $7,410,360 | $3,287,195 |
Totals | $55,759,232 | $28,535,797 |
MSBA UPDATES
- Executive Director Report
- Project Status
FINANCE
- Sales Tax Collection Update
- Grants Payments Update
- FY 20 Budget Update
- Authorization of 2020 Dedicated Sales Tax Bonds, Refunding Bonds and Cash Defeasance of Prior Bonds